
Case Study: Distribution Center ESFR & High-Bay Photometrics
An ESFR sprinkler layout, a passing hydraulic report, and a compliant high-bay lighting grid for a big-box distribution center.
The Brief
A general contractor landed a 65,000 sq ft distribution center on a tight build schedule: a 36-foot clear storage height, rack storage running nearly the full height, a dense roof-joist grid, and a fire department that would hold the certificate of occupancy until both the sprinkler system and the lighting were signed off. They needed two deliverables, and they needed them together: an ESFR sprinkler layout with a hydraulic report the fire department would accept, and a high-bay lighting design with a photometric grid proving adequate footcandles across the aisles and rack faces.
The job came to us with eight business days of float before the submittal deadline. We took both scopes in one coordinated pass — because in a warehouse, the sprinkler mains and the high-bay fixtures live in the same ten feet of ceiling, and drawing them separately is how conflicts get built.
Challenge: Storage Height Changes Everything
ESFR (Early Suppression Fast Response) protection is powerful, but it is picky. Heads under a 36-foot ceiling leave no room for improvisation: deflector clearances, maximum spacing, and the exclusion zones around obstructions are all measured in inches. The roof structure was a joist grid at 5-foot centers with chords, bridging, and a forest of small mechanical penetrations — exactly the kind of ceiling that turns a clean head layout into a field reroute if the drafter is not paying attention.
The storage arrangement added its own constraints. Rack aisles had to stay clear of drops, flue spaces had to remain unobstructed, and the uprights created a hard grid the head layout had to respect. Commodity classification drove the design criteria, and we confirmed the classification with the engineer of record before a single head was placed — guessing at commodity class is how ESFR submittals die in review.
On the lighting side, the challenge was the mirror image: high-bay fixtures had to deliver uniform footcandles down 36 feet to the aisle floor and the rack faces, with uniformity ratios the owner could accept, while staying clear of the sprinkler branch lines and the deflector exclusion zones. Light the aisles and you light the racks; get the mounting wrong and the racks shadow the aisles.
Solution: One Coordinated 2D Pass
We drafted both disciplines from the same rack-and-structure background in 2D AutoCAD, in this order:
- Shared background. Racking footprints, aisle widths, joist layout, and obstructions went on one coordinated base so both disciplines designed against the same building.
- ESFR head layout to NFPA 13. Heads placed for coverage under the 36-foot deck, coordinated to the joist grid, with branch lines routed to avoid flue-space violations and deflector obstructions. Every head got a tag that carried into the hydraulic node schedule.
- High-bay lighting layout. Fixture rows aligned to the aisles, not the joists — aisles are where the light has to land. Mounting heights and spacing were iterated against the photometric grid until the numbers held.
- Cross-discipline deconfliction. Sprinkler branch lines versus fixture rows, drops versus fixtures, head deflectors versus high-bay housings. The two systems were checked against each other on the plan, not discovered in the field.
The Hydraulic Report
The hydraulic calculation ran node by node from the most remote area back to the supply, comparing system demand against the municipal flow test the contractor provided. On the first run, demand sat uncomfortably close to the supply curve — close enough that a hot-day pressure dip could have pushed it over. We resized two cross-mains, re-ran the calc, and opened up a margin the fire department could accept. The final report shipped with the demand/supply graph, the node schedule, and the remote-area analysis — the package our sprinkler layout service produces as standard.
The Photometric Grid
The lighting package paired the layout with a point-by-point photometric study: footcandle grids at the aisle floor and at the rack faces, average/min/max values, and uniformity ratios. Two fixture spacings were tested; the tighter spacing won on uniformity at a modest fixture-count cost, and the grid proved it before anything was ordered.
Power Behind the Building
The building's electrical backbone — dock door power, office and restroom panels, equipment drops, and the service distribution — was drafted as a coordinated electrical system set with panel schedules and a single-line diagram, so the whole building read as one package at review.

Results
| Metric | Result |
|---|---|
| Building area | 65,000 sq ft |
| Sprinkler basis | ESFR, NFPA 13 |
| Hydraulic margin | Passed after cross-main resize |
| Lighting | Uniform footcandle grid at aisles and rack faces |
| Fire department review | Approved, no resubmittal |
| Turnaround | 9 business days |
Both packages cleared review together on the first submission, and the contractor kept the aggressive site schedule. The cross-main resize — a two-hour CAD change — is exactly the kind of decision that costs a week when it is discovered by the reviewer instead of the drafter.
Why It Worked
Three things made this submittal fast. First, the sprinkler and lighting scopes were drafted against the same background, so the deflector zones and the fixture rows never fought. Second, the hydraulic calculation ran before the layout froze, so pipe resizing was a design decision, not a correction response. Third, the photometric grid rode with the submittal instead of arriving as an afterthought — when the reviewer can see the numbers at the rack faces, there is nothing left to ask.
Have a warehouse or distribution project heading for review? Request a quote — send the building footprint and storage heights, and we will scope the sprinkler, lighting, and power package together.
Need similar drawings?
Get permit-ready fire protection drawings for your project
Send us your plans and scope — we'll come back with a fixed price and a turnaround date. No obligation.
Keep reading
Related articles
Fire ProtectionFire Alarm Drawings: Device Layouts, Risers, and Sequence Tables
A complete fire alarm permit package is more than device dots on a floor plan. Here is what we include on every set: spacing per NFPA 72, riser…
Fire Protection9 Sprinkler Head Layout Rules Every Drafter Should Know
NFPA 13 reads like an engineering manual, but on a plan it comes down to nine layout rules. Here is how we translate each one into head placement that…
Fire ProtectionSprinkler Hydraulic Calculations, Explained Simply
Density, area, and the demand-versus-supply graph — what a hydraulic calculation actually proves and the inputs you need to run one.
Get a fixed drafting quote in under 24 hours
Send us your architectural plans and scope. We'll come back with a fixed price and a turnaround date — no obligation.
